Transition zones between bridges and embankments are the most maintenance-prone locations in the road network of The Netherlands due to the very compressible soft soil layers that are widespread in the subsoil of the country. This aspect causes (differential) settlements at the ground surface, damage and maintenance costs for the road owner, and delays to road users. This paper provides the proof-of-concept of an innovative multi-source data-driven method based on the assimilation of both conventional settlement plate and satellite DInSAR data in numerical geotechnical modelling with the aim of supporting informed maintenance decisions.
Historically, the Netherlands have always been prone to subsidence due to the presence of very soft and compressible soils in the shallow subsoil layers, resulting in damage to both buildings and the infrastructure network. These layers, mainly composed by peat, organic clay and silt, are characterised by low stiffness, high compressibility and high creep rates (Den Haan and Kruse, 2006). Rijkswaterstaat, the Dutch National Road Authority, estimates that the money yearly spent on maintaining the transition zones between bridges and embankments sums up to about EUR 1.5 million corresponding to 1 %–2 % of the entire budget yearly allocated for subsurface-related maintenance works of all the road infrastructure (Dieteren, 2011; Venmans and Kwast, 2011). When the differential settlement between a bridge and its approach embankment reaches unacceptable values, the problem is commonly faced with the restoration of the road pavement through the addition of new asphalt layers without considering other possible solutions. The paper suggests a new approach in the analysis of settlements affecting infrastructure with the aim of helping the Road Authorities and the contractors in the decision-making process of future maintenance operations. The validation test was carried out by exploiting both conventional and DInSAR data sets. The latter represents nowadays a well-known technique to measure subsidence-induced ground displacements (Peduto et al., 2019) – with an accuracy of a few mm yr
The N3 is a Dutch road located in the south-western part of the Netherlands,
near the city of Dordrecht (Fig. 1a). The N3, with a length of approximately
10 km, is characterised by elevated embankments on top of which the road is
positioned. The presence of the embankments linked to the bridges allows
having cross-junctions with other network systems (Fig. 1b). Rijkswaterstaat
is planning different maintenance operations to take place in the next years. In particular, the N3 is scheduled to be maintained mainly all along its length between 2020 and 2022. The location selected for this study is identified in Fig. 1a with the red rectangle. The embankment (identified by the cross-section named A–A
The embankment construction took place from 25 May 1991 until the first months of 1993 by means of filling operations that raised the embankments with stages of 0.5 up to 1.0 m.
The soil stratigraphy and the cross sections of the embankment are depicted
in Fig. 1c. Five main soil types can be identified (from top to bottom): heavy clay (depth
The unit weights and the permeability the involved soils (Table 1) are known
from laboratory tests; the compression constants
Soil parameters.
The procedure followed consists of three phases. In Phase 1, all the available information on the selected location was collected. The geotechnical subsoil model of the embankment – deriving from the information concerning geometry, CPTs and laboratory tests – was implemented in the software D-Settlement (Visschedijk et al., 2016) to perform the settlement prediction. Phase 2 dealt with the calibration of the previously defined model. This phase was divided into two sub-phases: first, both conventional monitoring data (i.e. settlement plates) and DInSAR observations were merged. Then, these measurements were assimilated with the previously defined model in order to calibrate the initial predictions updated by the Maximum A-Posteriori estimate (MAP) method. Phase 3 dealt with the analysis of different maintenance scenarios based on the calibrated geotechnical model.
The knowledge on the real filling schedules of the embankment allowed simulating the real construction phases. The settlement prediction (see Fig. 2) in the period (1991–2019) from the start of the construction to present leads to an absolute settlement of 2.750 m including a post-construction settlement (1993–2019) equal to 0.280 m in the centre-line of the embankment (Fig. 2).
Predicted settlement of the centre-line of the embankment (vertical red-dashed line in Fig. 1c). Time is reported on a logarithmic scale.
The following monitoring datasets were combined: settlement plates (Fig. 1b)
covering the construction period from 1991 to 1992; DInSAR data (Fig. 3a),
covering the serviceability period from 1995 to 2018, deriving from the
processing of images acquired by 4 different satellites: ERS-2 (from 1995 to 2001), Envisat (from 2003 to 2010), Radarsat-2 (from 2010 to 2017) and
TerraSAR-X (from 2015 to 2018). DInSAR data were pre-processed by SkyGeo via a PSI-like algorithm (Ferretti et al., 2001). First, all available DInSAR
observations were merged (Fig. 3b) assuming a constant velocity in time (equal to the average velocity value derived from the linear regression of
each time series, see the solid lines in Fig. 3b) for the timespan for which
no data were available. Then, DInSAR time series were combined with the average measurements of the selected settlement plates. For this purpose,
the settlements predicted by the model were fitted to the settlement plates
information and the merged DInSAR observations were attached (Fig. 4) to the
value of the settlement prediction at the time of the first satellite
acquisition (i.e. Ers-2 in 1995). The combined observations were introduced in the D-Settlement model to calibrate the predictions of the model on the
observations by modifying the fitting factors. The absolute settlement in
the centre-line in 2019 after fitting is 2.531 m, with post-construction
settlement (1993–2019, the black-dashed line in Fig. 4) equal to 0.384 m. The fitting factors and the calibrated values of soil parameters are listed in Table 2. Phase 3 pursued three different settlement predictions (period 2019–2034) considering the following three scenarios:
The “do nothing” scenario (scenario 0 hereafter) assumes no maintenance works will take place in 2019. The “adding of asphalt” scenario (scenario 1 hereafter) assumes that the old asphalt pavement will be replaced by a new top layer in 2019. The new top layer entity will fully compensate the settlement during the period between 2009 and 2019 (i.e. around 0.06 m, see Table 3). The “EPS fill” scenario (scenario 2 hereafter) assumes the replacement of 1.50 m of the original sand fill by the lighter Expanded Polystyrene (EPS) Foam and the renewal of the approach slab above it.
Figure 5 depicts the results of the three-scenario analysis in terms of
predicted settlements up to 2034. Table 3 shows the values of post-maintenance settlements.
Comparison between the fitting carried out only with SP and the fitting made also with DInSAR data. Time is reported on a logarithmic scale.
Settlement predictions for the period 2019/2034.
Fitting factors and soil parameters after the calibration of the model.
Predicted cumulative total settlements for different scenarios.
The “do nothing” scenario does not require maintenance work, thus it is not considered in this phase. Indeed, this scenario was defined just to understand what could happen if nothing changes on the infrastructure. Referring to scenario 1, re-profiling the pavement with a new porous asphalt only requires the milling of the old pavement and the substitution with a new one. Referring to the scenario 2, it is important to note that the replacement of the original fill with the EPS is complex and time-consuming. It is worth stressing that the Road Authority prescribes that “the post-construction differential settlement of the embankment below an approach slab shall not exceed the 1 % out of the length of the approach slab” (Beukema, 2016). For the specific case of a 5 m long approach slab, the allowable differential settlement equals 50 mm. This means that every time a differential settlement higher than 50 mm is recorded between the bridge and the approach embankment, maintenance works are required.
In the period from 2019 to 2034, the predictions for scenario 1 suggest a differential settlement equal to 59 mm (see Table 3), meaning that additional maintenance works are needed since the requirement imposed by the road manager will be exceeded. For scenario 2, instead, the predicted post-maintenance settlement is 24 mm.
Time-histories for the three different cases.
Scenario analysis for the three cases.
The availability of monitoring observations covering the entire lifecycle of
an infrastructure, from the construction to nowadays, is almost a one-of-a-kind case. For the case study at hand, DInSAR data improved the
reliability of the predictions performed by the model. Information added by
this technique helped to better understand the performance of the embankment
during the creep phase that is usually not monitored by the conventional
systems. The drawback of DInSAR is the need of high resolution time-series
coverage and long timespan. This aspect can be problematic since only recent
very high-resolution sensors (e.g., TerraSAR-X, Cosmo-SkyMed) can ensure higher coverage and precision. Figure 6 shows the settlement time-history
for different cases: the red curve when both conventional and DInSAR data
are available (SP
The calibration performed by using only settlement plates leads to the lowest creep settlement. Looking at the case of calibration carried out by exploiting only DInSAR data the creep trend is similar to the ideal case in terms of inclination of the secondary settlement curve. The post-maintenance
settlement for scenarios 1 and 2 (S1 and S2) for the three calibration options are shown in Fig. 7. Table 4 summarises the total predicted settlements highlighting percentage differences from the SP
Predicted post-maintenance settlement for the three cases in the timespan 2019/2034.
The authors confirm that the data supporting the results of this study are available within the paper. The ownership of the raw data relating to DInSAR data used in this work belongs to SkyGeo Netherlands B.V. company.
All Authors contributed to this work by conceiving the idea, designing the methodology, performing the analyses that allowed to retrieve the presented results, writing and revising the paper.
The authors declare that they have no conflict of interest.
This article is part of the special issue “TISOLS: the Tenth International Symposium On Land Subsidence – living with subsidence”. It is a result of the Tenth International Symposium on Land Subsidence, Delft, the Netherlands, 17–21 May 2021.
SkyGeo company is gratefully acknowledged for providing DInSAR data.
This research has been supported by the ERASMUS